Main pool filled and operating, along with fountains and jets. Landscape ongoing 85% at the overall site with tree planting, shrubs, road work, fountain and hard scape. |
|
|
|
|
|
| |
| |
As of 1st of August 2011, overall site landscape is ongoing 85% with tree planting, shrubs, road work, fountain and hard scape. M&E final fix installed wares and fixtures at Condo A, B and C reached 88% and landscape is 90% complete. For condo D, the external render is ongoing 85% and internal render is ongoing 70%. |
|
|
|
|
|
|
|
|
| |
| |
The doors and windows have been completely installed in all 27 villas. |
|
|
|
|
|
|
| |
| |
The superstructure of condominium tower D is being erected quickly, with the fifth floor slab already poured. |
|
|
|
|
|
|
| |
| |
The windows and doors have been fully installed. |
|
|
|
|
|
|
| |
| |
The Condo blocks exteriors are completed and the interior fit-out is well underway. |
|
|
|
|
|
|
| |
| |
The doors and windows have been fully installed. |
|
|
|
|
|
|
| |
| |
The doors and windows have been fully installed. |
|
|
|
|
|
|
| |
| |
The superstructure of Condominium Block A is complete, with a total of 9 levels, including the ground floor. |
|
|
|
|
|
|
| |
| |
The superstructure of Condominium Block B is complete, with a total of 12 levels, including the ground floor. |
|
|
|
|
|
|
| |
| |
The superstructure of Condominium Block C is complete, with a total of 6 levels, including the ground floor. |
|
|
|
| |
| |
Superstructure Milestone Completion |
|
|
| |
| |
Superstructure Milestones for Condo Blocks A, B and C complete, with Roof Level already poured. |
|
|
|
|
|
|
| |
| |
The foundations for all nine hotel blocks are under construction. This photo shows construction at Hotel Block C. |
|
|
|
|
|
|
| |
| |
The roof slabs of all of the beachfront residential villas have been completed. |
|
|
|
|
|
|
| |
| |
The pad foundations of Block C are now complete. This photo shows that column cages are poured in the pad foundations so the stump columns can then be formed and poured. |
|
|
|
|
|
|
| |
| |
The superstructure of Block A is now towering over the site, with the 8th floor slab already poured. |
|
|
|
|
|
|
| |
| |
The construction of Condominium Block B is moving quickly. The team has just poured the concrete slab of level 6. |
|
|
|
|
|
|
| |
| |
Condominium Block C is quickly taking its shape, with the fourth floor slab just poured. |
|
|
|
|
|
|
| |
| |
Our industrious construction team has recently completed foundations for the exclusive Condominum Block C! |
|
|
|
|
|
|
| |
| |
Foundations for all 27 of the Hyatt Regency Danang Residences has been completed ahead of schedule. |
|
|
|
|
|
|
| |
| |
Foundations for Condominium Block A & B have been completed and the construction team is working diligently to begin constructing the superstructure by the end of July. |
|
|
|
|
|
|
| |
| |
Sales Office now open. We are pleased to advise that our sales office is now open onsite from 9am each day. |
|
|
|
|
|
|