Main Pool

  Main pool filled and operating, along with fountains and jets. Landscape ongoing 85% at the overall site with tree planting, shrubs, road work, fountain and hard scape.
  85% Completed

 

 
  Overview of Hyatt Regency Danang site - August 2011

  As of 1st of August 2011, overall site landscape is ongoing 85% with tree planting, shrubs, road work, fountain and hard scape. M&E final fix installed wares and fixtures at Condo A, B and C reached 88% and landscape is 90% complete. For condo D, the external render is ongoing 85% and internal render is ongoing 70%.
  90% Completed

 

 
  Residential Villas

  Doors and Windows
  100% Completed

  The doors and windows have been completely installed in all 27 villas.

 
  Condominium Block D

  Level 5 floor slab
  100% Completed

  The superstructure of condominium tower D is being erected quickly, with the fifth floor slab already poured.

 
  Condominium Block C

  Doors and Windows
  100% Completed

  The windows and doors have been fully installed.

 
  Condominium Blocks

  Exteriors
  100% Completed

  The Condo blocks exteriors are completed and the interior fit-out is well underway.

 
  Condominium Block A

  Doors and Windows
  100% Completed

  The doors and windows have been fully installed.

 
  Condominium Block B

  Doors and Windows
  100% Completed

  The doors and windows have been fully installed.

 
  Condominium Block A

  Superstructure
  100% Completed

  The superstructure of Condominium Block A is complete, with a total of 9 levels, including the ground floor.

 
  Condominium Block B

  Superstructure
  100% Completed

  The superstructure of Condominium Block B is complete, with a total of 12 levels, including the ground floor.

 
  Condominium Block C

  Superstructure
  100% Completed

  The superstructure of Condominium Block C is complete, with a total of 6 levels, including the ground floor.

 
  Condominium Blocks A, B and C

  Superstructure Milestone Completion
  100% Completed

  Superstructure Milestones for Condo Blocks A, B and C complete, with Roof Level already poured.

 
  Hotel Blocks

  Foundations
  100% Completed

  The foundations for all nine hotel blocks are under construction. This photo shows construction at Hotel Block C.

 
  Residential Villas

  Roof Slabs
  100% Completed

  The roof slabs of all of the beachfront residential villas have been completed.

 
  CONDOMINIUM BLOCK C

  Pad Foundations
  100% Completed

  The pad foundations of Block C are now complete. This photo shows that column cages are poured in the pad foundations so the stump columns can then be formed and poured.

 
  CONDOMINIUM BLOCK A

  Level 8 Slab
  100% Completed

  The superstructure of Block A is now towering over the site, with the 8th floor slab already poured.

 
  CONDOMINIUM BLOCK B

  LEVEL 6 SLAB
  100% Completed

  The construction of Condominium Block B is moving quickly. The team has just poured the concrete slab of level 6.

 
  CONDOMINIUM BLOCK C

  Level 4 Slab
  100% Completed

  Condominium Block C is quickly taking its shape, with the fourth floor slab just poured.

 
  Condominium Block C

  Foundations
  100% Completed

  Our industrious construction team has recently completed foundations for the exclusive Condominum Block C!

 
  Luxury Villas

  Foundations
  100% Completed

  Foundations for all 27 of the Hyatt Regency Danang Residences has been completed ahead of schedule.

 
  Condominium Blocks A & B

  Foundations
  100% Completed

  Foundations for Condominium Block A & B have been completed and the construction team is working diligently to begin constructing the superstructure by the end of July.

 
  Sales Office

  On Site Sales Office
  100% Completed

  Sales Office now open. We are pleased to advise that our sales office is now open onsite from 9am each day.